345 kV Transmission Lines & Switching Station
ITCTransmission will build a new 345 kV switching station and two 345 kV feeds to support a customer request from DTE Energy to provide power to a new 1 GW data center in Van Buren Township, Michigan, called Project Cannoli.
The new 345 kV feeds will connect ITC’s existing Brownstown – Wayne #1 and Brownstown – Wayne #2 345 kV lines to the proposed Cannoli switching station.
The first 345 kV feed is scheduled to be in-service late 2027, and the second 345 kV feed is scheduled to be in-service late 2028. Switching station construction will begin Q1 2028 and scheduled to be completed Q3 2028.
Click here to view the project profile (.pdf).
For project questions, please contact us at 248-365-4272 or cannoli@itctransco.com.
Construction updates can be found on the Van Buren Township website.