MICHIGAN THUMB

Michigan Thumb Loop 345kV Transmission Line

ITC Michigan, through its ITCTransmission subsidiary, completed the Thumb Loop high-voltage transmission project in May 2015. ITC invested $510 million to build the 345,000 volt (345 kV) line, which now serves as the backbone of a system designed to meet the identified maximum wind energy potential of Michigan’s Thumb region. It also is contributing to regional system reliability and facilitating wholesale market competition.

The Thumb Loop Project consists of approximately 140 miles of double-circuit 345,000 volt (345 kV) lines and four new substations that serve as the “backbone” of the system. Additional lines and facilities will be needed in the future as wind generators go into service and connect to the backbone system to fulfill the requirements of the state’s Renewable Portfolio Standard. The system is designed to meet the identified minimum and maximum wind energy potential of the Thumb region (2,367 and 4,236 MW respectively) and is capable of supporting a maximum capacity of about 5,000 MW. The new system was constructed in stages. The first segment, the western side of the loop from the Bauer substation in Tuscola County to the Rapson substation Huron County, went into service in September 2013. Phase two in St. Clair County, from the Fitz substation to Greenwood, went into service in May 2014. Phase 3, comprising 56 miles of line in Huron and Sanilac counties and the Banner substation near Sandusky, went into service in May 2015. 

WANT TO SEE ALL THE PROJECT DETAILS?

HOW DID YOU DETERMINE THE ROUTES?

ITC hosted open house events in July 2010 to present potential routes, discuss project details and receive feedback from affected landowners along each potential route. We then developed two routes, a proposed route and an alternate route. The proposed route minimizes the direct project impacts to the human and natural environment while providing a constructible and cost-efficient route. It also minimizes the potential indirect future impacts associated with construction of transmission lines to connect wind farms to the backbone transmission line. The alternate route would require construction of longer transmission lines to connect wind farms to the backbone transmission line because it is located more to the inner edge of the wind zone and follows an alignment through the more central area of the Thumb, rather than along the outer periphery where the highest potential for wind exists. Both routes attempt to avoid developed and municipal areas, state and public lands, center pivot irrigation systems, airports and landing strips. We tried to maximize distance from residences and minimize wetlands within the right-of-way. We also attempted to use existing ITC rights-of-way in areas where there are suitable and available adjacent lands for the additional right-of-way this project will require. When crossing cropland, we looked to locate the line along field borders, fence rows, non tilled borders or waterways. We also attempted to span across fields where possible, thus avoiding the need to place a structure within a tilled area. The MPSC approved the preferred route on February 25, 2011.

HOW DOES ITC WORK WITH LANDOWNERS?

ITC works respectfully with landowners throughout the siting, design, and construction process to minimize impacts to their properties

WILL I BE RESTRICTED ON WHAT ACTIVITIES I CAN PERFORM ON MY LAND?

ITC expects that in most cases land can be used for the same purposes for which it was used prior to the construction of the transmission line. Farming activities can continue under the line, with only the pole structure, a tubular steel monopole approximately every 900 feet, affecting agricultural activities.

WHAT WILL THE TRANSMISSION LINE LOOK LIKE?

The Thumb Loop project is being built primarily with tubular steel monopoles in a double-circuit arrangement with three double-bundled conductor phases for each circuit on either side of the pole. Steel lattice towers are being used for large angle applications. Overhead ground wires will be located at the top of the structures to protect the conductors from lightning strikes. The height of the structures varies based on terrain, clearances to the ground, objects under the line and structure spacing, but typically range between 130 and 180 feet. The span lengths between structures is approximately 800 to 1,100 feet, with an average span of 900 feet.

WILL THE THUMB LOOP 345-KIOLVOLT TRANSMISSION LINE BE SAFE?

345-kV transmission lines have operated safely in Michigan and across the entire country, around people and animals, since the 1950’s. ITC owns and safely operates 2,939 miles of 345-kV lines in Michigan. The Thumb Loop 345-kV project is being built to meet and/or exceed all applicable safety standards.

WILL THIS LINE EMIT ELECTRO-MAGNETIC FIELDS (EMF)?

Yes, EMF exist wherever there is a flow of electricity, including around power distribution and transmission lines, as well as around electrical wiring in homes and businesses, and electric appliances and equipment. Over the past 30 years, many scientific studies have been conducted on EMF and health. This research has been reviewed by leading public health agencies, such as the World Health Organization (WHO), which currently finds that “despite extensive research, to date there is no evidence to conclude that exposure to low level electromagnetic fields is harmful to human health.” If you have additional EMF questions, please contact ITC’s Customer Toll-Free Line at 877.ITC.ITC9 (877.482.4829).

SIGN UP FOR ITC NEWSLETTERS

Stay up-to-date with ITC activities throughout our footprint.

SIGN UP NOW

CAPITAL PROJECTS

Learn more about ITC capital projects across our footprint.

PROJECTS & INITIATIVES MAP

EXPLORE ITC CASE STUDIES

Follow ITC’s track record of success in helping our utility partners connect to the grid.

CASE STUDIES