Status: In Progress
-
Northridge Substation
ITC Holdings Corp., through its Michigan Electric Transmission Company, LLC (METC) subsidiary, is upgrading electricity transmission infrastructure in west Michigan. The existing high voltage electrical equipment in the outdated Four Mile 138kV station has been in-service for decades with aging equipment and limited reliability. The new 138kV Northridge substation will be built approximately 2.5 miles…
-
Brooks Industrial Interconnection Project
To support economic growth in south central Michigan, ITC Michigan, through its Michigan Electric Transmission Company (METC) subsidiary, is constructing a new substation, called Brooks Industrial, and 3.5 miles of new transmission lines in the City of Marshall, and in Marshall and Fredonia Townships. The project will connect to the existing Verona – Marshall 138,000…
-
Apex-Phoenix Transmission Line Project
A growing technology sector, excellent schools, and rich cultural and recreational opportunities make Ann Arbor a desirable place to live and work. This makes high-quality, reliable power increasingly important as homes and businesses are filled with sensitive electronics that can be affected by costly and inconvenient power outages. To support electric reliability and increase capacity…
-
Spearville-Axtell / KETA Project
The Spearville-Axtell line, also known as the KETA Project, is a 345,000 volt (345kV) transmission line that will improve the reliability and efficiency of the regional grid and make more affordable energy available. The line will run approximately 225 miles from Spearville north to the Post Rock (formerly Knoll) substation near Hays, then on across…
-
Toll Road Project
ITC’s Toll Road Project in Monroe County, Michigan, is providing greater system reliability and operational flexibility in the region. The project is being conducted in three phases: Phase I involved construction of the new 120 kV Toll Road Station, which includes 11 120 kV breakers and reconfiguration of the Fermi-Swan Creek circuit into the station….
-
Vestaburg – Alma Rebuild Project
ITC’s METC subsidiary is upgrading electricity transmission infrastructure in Michigan by rebuilding approximately 16 miles of its Vestaburg – Alma 138 kV transmission line, replacing the existing structures with new monopoles designed for higher-rated conductor (wire) and optical ground wire (OPGW). Additionally, METC will replace the conductor on 3 miles of the adjacent Eureka –…
-
Meyer Substation
ITC Holdings Corp., through its Michigan Electric Transmission Company, LLC (METC) subsidiary, has completed construction of the new Meyer substation in Wright Twp. The station connects to the existing Ludington – Tallmadge #1 and Argenta – Kenowa 345,000-volt (345kV) transmission lines, and the Cobb – Tallmadge #1 138,000-volt (138kV) transmission line. The station will be…
-
Riggsville – Port Calcite – Rockport Transmission Line Rebuild
In order to improve the reliability of high voltage electrical service in northern Michigan, ITC Michigan, through its Michigan Electric Transmission Company (METC) subsidiary, is rebuilding approximately 70 miles of the Riggsville – Port Calcite – Rockport 138,000 volt (138 kV) double circuit transmission line spanning the northeast lower peninsula. Construction is ongoing on the…
-
Blue Water Reinforcement Project
ITC Michigan is committed to serving customers and communities by providing safe, secure, reliable electricity transmission service to meet their needs. In Southeast Michigan, ITC has constructed two new 345kV substations, rebuilt four miles of an existing 120kV line, and replaced a number of structures on lines connecting to the new stations. Together, these infrastructure improvements…
-
Campbell – Tyler Project
ITC Michigan, through its Michigan Electric Transmission Company, LLC (METC) subsidiary, is upgrading electricity transmission infrastructure in west Michigan. METC will build approximately 4 miles of new 345,000 volt (345 kV) transmission line in an existing utility corridor. Additionally, new equipment will be installed in the Campbell and Tyler substations to facilitate the connection of…