The Green Power Express

The key goal of the Green Power Express™ was to serve as a catalyst to advance regional transmission in the north-central states and the U.S. by highlighting voids in the current regulatory framework around transmission planning and cost allocation. Announced in 2009, the Green Power Express served as a prime example of a large, multi-purpose transmission project for which no clear regulatory approval channel existed. The project played a central role in the development of the MVP portfolio, as well as the formation of MISO's cost allocation methodology.